An Alternative to EVM: The Zone Method

An Alternative to EVM: The Zone Method
By Michael D. Taylor

The Zone Method1 was developed as an alternative to the Earned Value Management (EVM) when projects cannot support the administrative load of EVM. The Zone Method uses two metrics, “schedule events” and “labor hours” to track project progress. A schedule event is defined as the measurable start or finish of a given activity. Since project costs are determined primarily by direct labor hours, most project managers find that costs can be tracked by tracking direct labor hours. These two metrics can reveal schedule and cost variances from the planned baseline. To determine the variances from the planned baseline one must accumulate the planned versus actual schedule events within a certain period of time (weeks, quarters, months, etc.). Once the planned schedule events have been established, the actual schedule events are subtracted to determine the variance of the schedule. The same idea holds for the variance of the cost of the project. Once the total planned and actual direct labor costs are compared, the variance can be determined by examining the difference between the two.

The Zone Method: Schedule vs Labor

The Zone Method Diagram
The Zone Method has received its name due to its four-quadrant graph that represents a projects positive or negative direct labor hours (or costs) and its positive or negative scheduled events. Each quadrant is recognized as a different state of the project. Directly in the center, the “bulls-eye” of the graph represents the perfect project that is both on time and on cost. The “green” zone is the area around the target (bulls-eye) with a variance of ±10%. If the project falls within this variance after 15% of the project time has elapsed, then the project is usually considered within an acceptable variance. If the project slips outside of this 10% variance (in any direction) the chances of completing the project on time, or on budget, diminish greatly.There are two yellow zones, one where the schedule variance is greater than 10% but the cost is less than 10%. The other yellow zone is a mirror image of the first, the project schedule variance is less than 10% but the cost variance is greater than 10%. If the project manager does not take action at this point it is likely that the project will migrate to the red zone where both the schedule and cost variances are greater than 10%. The red zone indicates a project which has a variance which is so large that is almost impossible to recover fully. The top-right quadrant is the “white zone” which represents favorable schedule and cost variances. Project in this zone are ahead of schedule by 10% and underrunning costs by 10%. While this may be deemed favorable, the project manager should examine this condition carefully since it may indicate poor planning.Zone Method Control Charts

Both metrics can be tabulated on a conventional spreadsheet as shown below. These tables show the planned versus actual schedule events and labor hours with the resulting variances. The variances can then be plotted over time to give a picture of the variance trends. By examining the trends, project managers can determine when corrective actions are required.

Planned Versus Actual Schedule Events

Planned vs Actual Schedule Events

Planned Versus Actual Labor Hours

Planned vs Actual Labor Hours

Variance Trends: Schedule Events and Labor Hours

Variance Trends: Schedule Events and Labor Hours

The Zone Method has advantages in that it is highly effective and has a very low administrative load. After converting the Gantt Chart to cumulative schedule events there is little else one has to do other than to regularly compare planned schedule events to actual schedule events. The same is done for labor hours. Because of this, and the fact that this method can be accomplished using conventional spreadsheets, it offers a viable alternative to the EVM method which may require a relatively large administrative load in light of the project budget.

1The Zone Method was developed by Systems Management Services.

MICHAEL D. TAYLOR, M.S. in systems management, B.S. in electrical engineering, has more than 30 years of project, outsourcing, and engineering experience. He is principal of Systems Management Services, and has conducted project management training at the University of California, Santa Cruz Extension in their PPM Certificate program for over 13 years, and at companies such as Sun Microsystems, GTE, Siemens, TRW, Loral, Santa Clara Valley Water District, and Inprise. He also taught courses in the UCSC Extension Leadership and Management Program (LAMP), and was a guest speaker at the 2001 Santa Cruz Technology Symposium. His website is www.projectmgt.com.

PMHut Team

PMHut Team

PMHut.com is a website dedicated to providing PM articles, detailed project management software reviews, and the latest news for the most popular web-based collaboration tools.

2 Responses

  1. Hi Michael,
    Unless I have totally missed something, your article, while well written and certainly interesting, IMPO, misses entirely the point of Earned Value Management!!

    The fundamental principle behind EVM is WHAT DID WE GET FOR WHAT WE PAID. As I understand your approach, you are attempting to compare the planned vs the actuals only, correct? If yes, I fear this will give you only part of the picture, and IMPO, a dangerously false or misleading part of the picture, as it totally ignores what work was actually accomplished in that time period for the money spent.

    To help understand it better, is there ANY direct relationship between money spent and physical percent complete? In other words, if 50% of the money has been spent, does that mean 50% of the project is completed? Or is there any direct correlation between elapsed time and physical percent complete? Explained another way, if 30% of the allowed time has elapsed, does that necessarily mean the project is 30% complete?

    Assuming you agree the answer to both questions is no, then how can you assume that by comparing the cost variance (either in money or in hours) against the time variance, that it will tell you anything meaningful about the project, without knowing how much work was actually accomplished?

    Your graph, while a fundamentally sound concept, is, IMPO, using the wrong information. Instead of plotting the Cost Variance, (CV = EV – AC) try plotting the Cost Performance Index (CPI=EV/AC) and instead of plotting the Schedule Variance (SV = EV-PV), try plotting the Schedule Performance Index (SPI = EV/PV)

    Bottom line on all this- Earned Value, if implemented in a rational and simple manner, is no more onerous or bureaucratic that balancing your check book each month and I can promise you, it will tell you a whole lot more about your project than what I believe you are proposing?

    BR,
    Dr. PDG, Kuala Lumpur, Malaysia

  2. Avatar Michael Taylor says:

    Dr. Giammalvo: Your comments are well taken and correct if you assume that the Zone Method is a replacement for EVM. However, as stated in my article, that is not the point. I still believe EVM is the best tracking method available, but many of my students have cited conditions where EVM is an overkill, and the administrative load too great. For that reason the Zone Method is an alternative to EVM,not a replacement for EVM. mdt

Leave a Reply