Supporting Frameworks for Successful Program Management – Material Management

Supporting Frameworks for Successful Program Management – Material Management (#19 in the series Foundations, Frameworks and Lessons Learned in Program Management)
By Robert Prieto

Program management affords the opportunity to leverage procurement of select materials and services across multiple projects. Concomitant with such a strategy is the need to track, receive, store and dispatch such materials across multiple projects at multiple points in time until such materials have been incorporated into the permanent construction. Comprehensive material management employing a fully integrated suite of tools to address each step in the material management process is essential. Material acceptance and testing activities may also be integral to such processes deployed on a program wide basis.

Robert Prieto, Senior Vice President

Robert Prieto is senior vice president for Fluor, where he leads strategy for Fluor’s Industrial and Infrastructure group. Mr. Prieto focuses on the development and delivery of large, complex projects worldwide.

Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. As head of PB’s board of directors, he was responsible for overseeing management performance, establishing top-level policies, and ensuring the firm’s continued long term success.

He is a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the board of directors of the Business Council on International Understanding, a member of the board of the Civil Engineering Forum for Innovation, and co-founder and member of the board of the Disaster Resource Network. He currently serves on the National Research Council’s committee framing the challenges on Critical Infrastructure Systems. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He is also a member of the board of trustees of Polytechnic University of New York, and was previously selected as alumni of the year by its New York Chapter.

He has had an executive sponsorship role in the World Trade Center Transportation Hub; West Coast Rail Modernization; Train Protection and Warning System; Level 3 Communications Long Haul Network and Superconducting Super Collider.

Prieto holds a master of science in nuclear engineering from Polytechnic University of New York and a bachelor of science in nuclear engineering from New York University.

Fluor Corporation (NYSE: FLR) provides services on a global basis in the fields of engineering, procurement, construction, operations, maintenance and project management. Headquartered in Irving, Texas, Fluor is a FORTUNE 500 company with revenues of $14.1 billion in 2006. For more information, visit www.fluor.com.

PMHut Team

PMHut Team

PMHut.com is a website dedicated to providing PM articles, detailed project management software reviews, and the latest news for the most popular web-based collaboration tools.

Leave a Reply