Types of Construction Cost Estimates
Types of Construction Cost Estimates (#14 in the Hut Project Management for Construction)
By Chris Hendrickson
Construction cost constitutes only a fraction, though a substantial fraction, of the total project cost. However, it is the part of the cost under the control of the construction project manager. The required levels of accuracy of construction cost estimates vary at different stages of project development, ranging from ball park figures in the early stage to fairly reliable figures for budget control prior to construction. Since design decisions made at the beginning stage of a project life cycle are more tentative than those made at a later stage, the cost estimates made at the earlier stage are expected to be less accurate. Generally, the accuracy of a cost estimate will reflect the information available at the time of estimation.
Construction cost estimates may be viewed from different perspectives because of different institutional requirements. In spite of the many types of cost estimates used at different stages of a project, cost estimates can best be classified into three major categories according to their functions. A construction cost estimate serves one of the three basic functions: design, bid and control. For establishing the financing of a project, either a design estimate or a bid estimate is used.
- Design Estimates. For the owner or its designated design professionals, the types of cost estimates encountered run parallel with the planning and design as follows:
- Screening estimates (or order of magnitude estimates)
- Preliminary estimates (or conceptual estimates)
- Detailed estimates (or definitive estimates)
- Engineer’s estimates based on plans and specifications
For each of these different estimates, the amount of design information available typically increases.
- Bid Estimates. For the contractor, a bid estimate submitted to the owner either for competitive bidding or negotiation consists of direct construction cost including field supervision, plus a markup to cover general overhead and profits. The direct cost of construction for bid estimates is usually derived from a combination of the following approaches.
- Subcontractor quotations
- Quantity takeoffs
- Construction procedures.
- Control Estimates. For monitoring the project during construction, a control estimate is derived from available information to establish:
- Budget estimate for financing
- Budgeted cost after contracting but prior to construction
- Estimated cost to completion during the progress of construction
Next in the Hut Project Management for Construction:
Design Estimates in Construction Project Management
Previously in the Hut Project Management for Construction:
Approaches to Cost Estimation in Construction Project Management
Chris Hendrickson is the Duquesne Light Company Professor of Engineering and Co-Director of the Green Design Institute at Carnegie Mellon University. His research, teaching and consulting are in the general area of engineering planning and management, including design for the environment, project management, transportation systems, finance and computer applications. Prof. Hendrickson is a Distinguished Member of the American Society of Civil Engineering, an Emeritus Member of the Transportation Research Board and a Fellow of the American Association for the Advancement of Science. Hendrickson is also the recipient of many professional awards.
1 Response
[…] Types of Construction Cost Estimates […]