What Is Early Finish Date (EF)?

What Is Early Finish Date (EF)? – Early Finish Date (EF) is, in the critical path method, the earliest possible point in time on which the uncompleted portions of an activity (or the project) can finish based on the network logic and any schedule constraints. Early finish dates can change as the project progresses and changes are made to the project plan.